Decisions / Town of Greater Napanee
Quinte Energy Storage Centre (near 2911 County Road 22)
Council supported the project for procurement on May 12, 2026.
Council backed a municipal support resolution despite a conservation authority warning about significant uncertainties. The resolution's stated sole purpose is to meet IESO requirements; it is not a construction approval.
- Municipality
- Town of Greater Napanee
- Decided by
- Council
- Meeting date
- Developer
- Hydrostor
- Type
- Compressed-air storage
- Size
- 500 MW
- Procurement
- IESO Long Lead-Time (LLT) RFP
- Vote
- Not reported in the source
What this decision does and does not do
A support resolution or confirmation lets the developer bid into an IESO procurement. It is not a planning approval: zoning, site plan and provincial permits still apply if the project wins a contract.
Sources
No official decision minutes or municipal recap currently linked. A staff report alone does not establish a council vote. About evidence classifications.
- ‘Significant uncertainties’: Napanee backs Hydrostor project despite conservation authority warningKingstonist, May 13, 2026 · Third-party reporting or commentary
Spot an error? Send a correction with a link to the record that shows it.