Council refused support on Sept. 24, 2025.

Council declined to pass a support resolution, saying support outside the planning process would put the cart before the horse. It asked staff to draft a community benefit strategy and to tell the IESO the process is flawed.

Municipality
Township of Puslinch
Decided by
Council
Meeting date
Developer
Integrative Project Solutions Ltd.
Type
Solar
Size
5 MW
Procurement
IESO LT2 Window 1 (Energy)
Vote
Not reported in the source

What this decision does and does not do

Without municipal support the project cannot bid in procurements where support is mandatory, as it is for LT2 Window 2. A refusal applies to this request; a developer can return with a revised proposal.

Sources

No official decision minutes or municipal recap currently linked. A staff report alone does not establish a council vote. About evidence classifications.

Spot an error? Send a correction with a link to the record that shows it.

Other decisions in Township of Puslinch