Mount Baldy 1 and 2

Council refused support on Nov. 2025.

Council voted against a municipal support resolution. The CAO had advised against issuing any support in the December 2025 intake because the deadline left too little time for proper evaluation.

Municipality
Municipality of Shuniah
Decided by
Council
Meeting date
(month only)
Developer
PowerBank Corporation (formerly SolarBank)
Type
Battery storage
Size
400 MW, 3.2 GWh; two 200 MW sites
Procurement
IESO LT2 Window 1 (Capacity)
Vote
Not reported in the source

What this decision does and does not do

Without municipal support the project cannot bid in procurements where support is mandatory, as it is for LT2 Window 2. A refusal applies to this request; a developer can return with a revised proposal.

Sources

No official decision minutes or municipal recap currently linked. A staff report alone does not establish a council vote. About evidence classifications.