Battery storage at 465 Wright Blvd.
Council supported the project for procurement on Dec. 8, 2025.
Council gave in-principle support through a municipal support resolution, for procurement purposes only. Site plan control and other municipal processes still apply.
- Municipality
- City of Stratford
- Decided by
- Council
- Meeting date
- Developer
- Cordelia BESS Inc.
- Type
- Battery storage
- Size
- 8.8 MW, 110 MWh
- Procurement
- IESO LT2 Window 1 (Capacity)
- Vote
- Carried, one councillor opposed
What this decision does and does not do
A support resolution or confirmation lets the developer bid into an IESO procurement. It is not a planning approval: zoning, site plan and provincial permits still apply if the project wins a contract.
Sources
No official decision minutes or municipal recap currently linked. A staff report alone does not establish a council vote. About evidence classifications.