Bolton Power Plant
Council supported the project for procurement on Dec. 17, 2025.
Council carried motion 36-12-2025 supporting submission of Bolton Manor Resilient Generation 2.0 Inc.'s Bolton Power Plant, a proposed biogas-fuelled reciprocating-engine expansion of an existing farm digester at 155532 15th Line. The motion lists 5.07 MW maximum potential contract capacity; staff Report 2025-126 states 3.3 MW. The figures conflict, and the support resolution is for an LT2 bid only, not a procurement award or construction approval.
- Municipality
- Township of Zorra
- Decided by
- Council
- Meeting date
- Developer
- Bolton Manor Resilient Generation 2.0 Inc.
- Type
- Biogas generation
- Size
- 5.07 MW, Carried Council motion 36-12-2025 lists 5.07 MW maximum potential contract capacity; staff Report 2025-126 describes 3.3 MW. The discrepancy is unresolved; neither figure is an IESO contract award.
- Procurement
- IESO LT2 Window 1 (Capacity; project LT2c1-6686)
- Vote
- Carried; recorded vote count not published
What this decision does and does not do
A support resolution or confirmation lets the developer bid into an IESO procurement. It is not a planning approval: zoning, site plan and provincial permits still apply if the project wins a contract.
Sources
Official meeting minutes linked. About evidence classifications.
- Zorra Council minutes, December 17, 2025, resolution 36-12-2025, pp. 5–7 (adopted January 22, 2026)Township of Zorra · Official meeting minutes
- Report 2025-126: Bolton Power Plant LT2 Biogas-Fueled Reciprocating Engine, pp. 95–98 of December 17 agenda packageTownship of Zorra · Official background (not proof of vote)