Civic Evidence

Decisions / City of Ottawa

South March (Marchurst Road) battery storage facility

Council granted a land-use approval on Dec. 2025.

Council granted zoning approval, moving the project into detailed technical, safety and site plan review. This is a land-use approval, not a support resolution.

Municipality
City of Ottawa
Decided by
Council
Meeting date
(month only)
Developer
Evolugen (Brookfield Renewable), with the Algonquins of Pikwàkanagàn First Nation
Type
Battery storage
Size
250 MW
Procurement
IESO E-LT1 / LT1 (contract already awarded)
Vote
21–4

What this decision does and does not do

This is a land-use decision, such as zoning, that lets the project move to detailed review. It is separate from, and usually later than, a support resolution.

Sources

No official decision minutes or municipal recap currently linked. A staff report alone does not establish a council vote. About evidence classifications.

Spot an error? Send a correction with a link to the record that shows it.

Project decision history

These are separate recorded actions concerning the same named project, not a single final project status.

  1. Committee vote (not final council decision): Refused. Evidence

  2. Council decision: Supported. Evidence

  3. Council land-use approval: Land-use approval (this record). Evidence

A committee vote is not necessarily the final council decision. Municipal support and land-use approval are different steps; neither demonstrates that construction is complete. Every step links to its own evidence.

Other decisions in City of Ottawa